At the same time that Keith was putting the metal lath on, Solid Ground (electrical contractor) and Pioneer Telephone arrived (magic co-ordination) and put in their cables, etc., so that we were able to fill in the trench. Meanwhile I cut one of the doors off of the upper container (the only way to remove one) and then poured the thin slab on what will be the balcony. The slab was poured on top of a sheet of container siding that we cut out of the 40 footer when we opened up the living room.